Kitchen Renovation Timeline in Melbourne: What to Expect Week by Week

VicWide Renovations Team9 min readUpdated January 8, 2026
Kitchen Renovation Timeline in Melbourne: What to Expect Week by Week
Representative editorial image. An illustration of this planning topic, not a completed VicWide project.

Most Melbourne homeowners ask two questions before signing a kitchen renovation contract: how much will it cost, and how long will we be without a kitchen. The second question is often answered too optimistically. A well-run kitchen renovation with no layout changes typically takes four to six weeks on site, but the full journey from first design meeting to final handover usually spans three to four months once joinery lead times and selections are counted.

This guide walks through the realistic sequence week by week, explains why some stages cannot be compressed, and flags the points where Melbourne projects most commonly lose time. If you understand the program before demolition starts, you will make faster decisions, avoid mid-build variations and keep every trade moving.

In this guide

The Real Timeline Starts Before Demolition

The on-site build is only the visible part of a kitchen renovation. The weeks before site start determine whether the build runs smoothly or stalls waiting for materials.

  • Design and layout (2-4 weeks): Measuring, concept drawings, revisions and final sign-off. Layout changes after this point become expensive.
  • Selections (1-3 weeks, often overlapping): Cabinetry colours, benchtop material, splashback, tapware, handles, appliances and lighting. Every unmade selection becomes a future delay.
  • Joinery fabrication (3-6 weeks): Custom cabinetry is manufactured to order. Most Melbourne joinery workshops quote four to five weeks from confirmed drawings, longer in the pre-Christmas rush.
  • Trade scheduling: Plumbers, electricians, plasterers, tilers and stone fabricators are booked in sequence before demolition begins.

A builder who starts demolition before cabinetry is in fabrication is gambling with your program. The strongest projects strip out the old kitchen only when the new one has a confirmed manufacturing date.

Week-by-Week Program at a Glance

StageTypical TimingKey ActivitiesWhat Can Go Wrong
Demolition and strip-outWeek 1, days 1-2Old kitchen removed, services capped, waste cartedHidden water damage, asbestos in pre-1990 homes, brittle old wiring
Rough-inWeek 1, days 3-5Plumbing and electrical moved to new positions behind wallsSlab drainage changes, switchboard upgrades in older homes
Plaster, prep and flooringWeek 2Walls patched or resheeted, surfaces levelled, floors repairedOut-of-level floors and walls in period homes needing extra prep
Cabinetry installationWeek 3Carcasses, doors, panels and kickboards installed and levelledLate joinery delivery, site measure discrepancies
Benchtop template and fabricationWeeks 3-4Stone templated after cabinets are fixed, then fabricated off siteThe 5-10 day fabrication gap that surprises most owners
Benchtop install and splashbackWeeks 4-5Tops installed, splashback tiled or fitted, sink cut-outs completedTile lead times, glass splashback measure-and-make delays
Fit-off and handoverWeeks 5-6Tapware, appliances, lighting, painting, silicone and commissioningMissing appliances, back-ordered tapware, final trade availability

The table assumes a same-footprint renovation. Wall removals, window changes or slab plumbing work can add two to four weeks and may require a building permit through a registered building surveyor.

Week 1: Demolition, Strip-Out and Rough-In

Demolition is fast. A standard Melbourne kitchen is usually stripped in one to two days, including benchtops, cabinetry, splashback and sometimes flooring. Services are capped, and the room is taken back to a shell.

The rest of the first week belongs to the plumber and electrician. Rough-in means running new pipework and cabling to the positions shown on the final drawings before walls are closed up.

  • Plumbing rough-in: Sink, dishwasher, fridge water point and any gas alterations. Moving a sink across the room is a much bigger job than most owners expect, particularly on a concrete slab.
  • Electrical rough-in: New circuits for ovens and induction cooktops, power points to current requirements, lighting cabling and switch positions.
  • Inspections and surprises: Older homes in suburbs like Brunswick, Preston and Essendon frequently reveal degraded wiring, undersized switchboards or unauthorised past work once walls open. Allow contingency for this.

Homes built before 1990 may contain asbestos sheeting behind splashbacks or in wall linings. Licensed removal is a legal requirement in Victoria and can add several days, so a pre-demolition inspection is money well spent.

Week 2: Plaster, Surfaces and Preparation

Week two rarely photographs well, but it decides the quality of everything that follows. Cabinetry and benchtops are manufactured square and level; period Melbourne homes are usually neither.

  • Plastering: Chased walls are patched, damaged sheets replaced, and new walls sheeted and set. Drying time between coats cannot be rushed, especially in cold, damp Melbourne winters.
  • Floor preparation: Levelling compound, repairs to boards, or new substrate where flooring is being replaced. An out-of-level floor telegraphs into visibly sloping benchtops.
  • Priming and first paint: Ceilings and wall areas that will sit behind or above cabinetry are painted now, because access disappears once joinery is installed.

If your renovation includes replacing floors through adjoining living areas, this is usually when that work is sequenced, and it can extend the stage by several days.

Week 3: Cabinetry Installation

Cabinet install day is the emotional turning point of the project. A full kitchen of custom joinery typically takes two to four days to install properly.

Installers level every carcass against the worst point of the floor, pack and scribe against uneven walls, and align doors and drawer fronts to consistent gaps. Tall towers, integrated appliance housings and panel-ready fridge cavities take longer than standard base runs because tolerances are tighter.

Resist the urge to judge the kitchen at this stage. Without benchtops, kickboards and handles the room always looks unfinished, and there is deliberately no rush to fit doors perfectly until heavier trades are done working around them.

Weeks 3 to 5: The Benchtop Gap Nobody Warns You About

Stone benchtops cannot be measured accurately until cabinets are permanently fixed. The fabricator visits site, creates a digital template, then manufactures the tops off site. That gap is typically five to ten business days, and it is the single most common source of timeline frustration.

  • Template: Booked once cabinetry is level and fixed, usually early in week three or four.
  • Fabrication: Cutting, edge profiling, cut-outs for sinks and cooktops. Complex work such as waterfall ends, mitred edges and full-height splashback panels adds days.
  • Installation: Usually completed in one day, after which the plumber can fit the sink and the splashback trade can begin.

Good builders use this gap productively: painting, flooring finishes, appliance deliveries and external works are scheduled into the same window rather than leaving the site idle.

Weeks 5 to 6: Splashback, Fit-Off and Handover

Once benchtops are in, the finish trades sweep through in sequence. Tiled splashbacks typically take one to two days plus grouting. Measured glass splashbacks need their own template-and-make cycle of one to two weeks, which is why glass is ordered as early as possible.

  • Plumbing fit-off: Sink, tapware, dishwasher connection and any filtered water or gas cooktop commissioning by a licensed plumber.
  • Electrical fit-off: Appliances connected, lighting and switch plates installed, safety switches tested and a certificate of electrical safety issued.
  • Final detailing: Kickboards, end panels, handles, silicone joints, door adjustment and touch-up painting.
  • Handover: Walkthrough, defect list, appliance demonstrations and warranty documentation.

Expect a short defect period after handover. Doors settle, silicone cures and small adjustments are normal in the first weeks of use.

What Commonly Delays Melbourne Kitchen Projects

Most delays are predictable, which means most are preventable.

  • Late selections: The number one cause. An unchosen tap or tile stops a trade, and rebooking that trade can cost a week, not a day.
  • Appliance lead times: Imported European appliances can carry long waits. Purchase early and store them, because cabinetry is built around exact appliance dimensions.
  • Structural discoveries: Removing walls brings engineering, possible permit requirements under the Victorian Building Authority framework, and steel fabrication time.
  • Trade sequencing failures: If the tiler misses their slot because the benchtop ran late, every following trade shuffles. Coordination is the real product a renovation builder sells.
  • Seasonal pressure: The pre-Christmas period stretches every joinery workshop and stone fabricator in Victoria. A November start is often better run as a January start.

Ask any prospective builder to show you a written program with trade sequence and joinery milestones. The quality of that answer tells you a great deal about how your project will actually run.

Take these ideas with you.

  • A same-footprint Melbourne kitchen typically takes 4-6 weeks on site, but 3-4 months door to door including design and joinery fabrication
  • Demolition should not start until cabinetry has a confirmed manufacturing date
  • The benchtop template-to-install gap of 5-10 business days is the most commonly overlooked stage
  • Late selections and appliance lead times cause more delays than trade workmanship ever does
  • Structural changes add engineering, permit and steel time, so treat them as a different program entirely

A few more answers

Questions about your next step.

How much should I budget for a kitchen renovation in Melbourne?

Budget depends on layout changes, cabinetry level, benchtop choice, appliance scope and trade complexity. Fixed-layout refreshes sit much lower than structural redesigns with new services.

What kitchen upgrades usually add the most practical value?

Better drawer storage, smarter appliance placement, durable benchtops, layered task lighting and a well-sized rangehood tend to outperform cosmetic-only upgrades.

How long does a kitchen renovation usually take?

Most kitchens run over several weeks. Cabinetry manufacturing, stone templating and trade sequencing usually matter more than the demolition day.

Put your ideas into a plan

Check feasibility before you lock a quote

Council overlays, access and existing services change the job. Bring the property constraints in before finish selections harden.

Want a written week-by-week program before you commit, not after? We plan every kitchen around joinery milestones and locked selections so the site never sits idle. See how our kitchen renovation process works.

Get my free quote

Before and after

See the change in the room.

Drag to explore the possibilities.

Warm oak kitchen before — illustrative concept
Warm oak kitchen after — illustrative concept
BeforeAfter
Cottage kitchen before — illustrative concept
Cottage kitchen after — illustrative concept
BeforeAfter
Family kitchen before — illustrative concept
Family kitchen after — illustrative concept
BeforeAfter

In our customer's words

Hear it from a
Melbourne homeowner.

A real customer shares her experience with VicWide Renovations.

Get my free quote
Mya Mokds6 days ago
I recently had renovation work done and I'm really happy with the results. The team was professional, friendly, and easy to communicate with. They listened to what I wanted and made sure everything was done properly.
Gary Saundersa year ago
Highly recommend VicWide Renovations. The job they did was amazing, all the guys were very professional and worked hard to bring the results me and my family wanted and needed.
Patrick Aramia7 months ago
From start to finish, the process was smooth and professional. The crew was punctual, respectful of my space, and incredibly skilled. The quality of work exceeded my expectations.
Lavina Dilip2 years ago
One of the best decisions we made choosing Steve and Ray to renovate our house. Such an amazing and dedicated team. Would recommend them to anyone looking for renovators around Victoria.
Raeda Gorgos6 days ago
Thanks to Steve and Kevin for their great service provided on renovation my bathrooms.
Neno Curica year ago
It was an absolute pleasure dealing with Steve and his guys at VicWide Renovations. Fast, efficient, good quality work and addressed any issues we had along the way without any fuss.
Mark4 days ago
Steve and Kevin did an outstanding job at my parents' old place—highly recommend them!
Deb Harrisa year ago
Great work from a friendly bunch of tradies. Am totally over the moon with the quality and finishes. Once I've saved up some additional funds more work coming their way.

Get started

Your ideas. A clear plan for your home.

1300 173 622

Tell us about your renovation

We'll only use your details to discuss your project.